May 24th - Demolition is under way

June 7th - Site prep is almost done

June 14th - Walls are going up

June 22nd - Hard at work

June 29th - More Walls! You can now see where the restaurant will be as well as where most of the auditoriums will be.

July 12th - Really starting to pick up speed. 

July 19th - Plumbing and Electrical starting to go in. 

July 26th - Starting to come together.

August 2nd - Slowly but surely, they are chipping away at it.

August 10th - Chugging along.

August 16th - Drywall is starting to go up.

August 23rd - Let there be walls.

August 30th - Getting roughed in.


September 7th - The Mezzanine is in


Kitchen Hood & Bar Front going in


September 21st - Drywall going up in the auditoriums, project is really starting to come together!


September 28th - More & More Drywall!!

October 10th - A lot is done and a lot is still left to do.